The SAP C-TS412-2021 exam is aimed at professionals who have experience in implementing and working with SAP S/4HANA Project Systems. The SAP S/4HANA Project Systems is a module of SAP S/4HANA that supports project management and execution. The module offers a structured and efficient approach to project planning, execution, monitoring, and control. It allows organizations to define and manage project resources, costs, timelines, and workflows.
NEW QUESTION # 62
Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question
- A. Capacity requirements
- B. Project-relevant purchase orders
- C. Production orders assigned to WBS elements
- D. Maintenance orders assigned to an activity
Answer: A,D
Explanation:
The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other objects such as WBS elements, networks, activities, milestones, production orders, sales orders, purchase orders, and so on. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002
NEW QUESTION # 63
Which report can use user-specific layouts?
- A. Hierarchical report
- B. Line item report
- C. Cost element report
- D. Enhanced individual overview
Answer: B
NEW QUESTION # 64
Material
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.
- A. The material have no material number.
- B. The procurement type in the material master is set to in-house Production.
- C. The item category of the materials is set tnon-stock item.
- D. The item category of the materials is set tstock item.
Answer: B,D
NEW QUESTION # 65
The system status of a WBS element is created (CRTD). Which business process is allowed for this NBS element
- A. Calculation of actual values
- B. Creation of purchase orders
- C. Activity allocation
- D. Goods receipt for purchase order
Answer: B
NEW QUESTION # 66
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?
- A. The system automatically creates a new purchase requisition with the difference to the original quantity
- B. A workflow can be triggered to inform the purchasing group.
- C. The purchase order is updated automatically to match the new quantity while saving the project.
- D. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)
Answer: C
NEW QUESTION # 67
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct answers to this question.
- A. Purchase order items
- B. Sales order items
- C. Reservations
- D. Internal orders
Answer: A,C
Explanation:
Project-Oriented Procurement (ProMan) is a tool that allows you to display and process procurement documents that are relevant for projects. You can use ProMan to display reservations and purchase order items that are assigned to WBS elements or network activities. You can also use ProMan to create purchase requisitions, purchase orders, goods movements, and invoices for project-related materials and services. Reference: https://help.sap.com/saphelp_erp60_sp/helpdata/EN/8e/8bc95360267214e10000000a174cb4/frameset.htm
NEW QUESTION # 68
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Project profile
- B. Network type
- C. Parameters for the network type
- D. Network profile
Answer: C
NEW QUESTION # 69
Cost and budget
A customer works in a multinivel production environment with bill of material and routing. To avoid unnecessary stock cost , they do not want to produce..
Which setup do you recommend?
- A. Assign Several production orders to a sales order
- B. Assign a sales order to a project with appropriate hierarchy levels.
- C. Assign One production order to a sales order
- D. Assign a network to a sales order
Answer: B
Explanation:
To avoid unnecessary stock cost, you can assign a sales order to a project with appropriate hierarchy levels. This means that you can create a project structure that matches the multilevel production environment with bill of material and routing. You can assign a sales order item to a WBS element that represents the finished product and assign production orders to WBS elements that represent the semi-finished products. This way, you can use project stock to manage the materials required for the project and avoid creating inventory for intermediate products. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
NEW QUESTION # 70
Project Structures
You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?
- A. The field key is the default value for the WBS element and the activities too.
- B. The field key is the default value only for the WBS element.
- C. The field key is hard coded in the WBS element.
- D. The tab user fields is invisible.
Answer: A
Explanation:
The benefit of assigning a field key to the project profile is that the field key is the default value for the WBS elements and the activities too. A field key is an object that defines which user fields are available and mandatory for a project object, such as a project definition, a WBS element, or an activity. A project profile is an object that contains various default values and control parameters for a project. By assigning a field key to a project profile, you can ensure that all WBS elements and activities created under that project profile have the same user fields settings. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/df72bb53707db44ce10000000a174cb4.html
NEW QUESTION # 71
Resources
How can you define external task in your project.
Note : there are 2 correct answers for this question.
- A. Assign a purchase order for external processing to the project definition.
- B. Create an external activity in a network.
- C. Create a service milestone.
- D. Create a service activity in a network.
Answer: B,D
Explanation:
"You can create external activities in a network to represent tasks that are performed by external service providers or vendors." According to SAP Press4, "You can create service activities in a network to represent tasks that are performed by internal service providers." Reference: 4
NEW QUESTION # 72
Which of the following is used to plan basic dates manually for WBS elements? Choose the correct answers. There are 2 correct answers to this question.
- A. Project Builder
- B. Schedule Manager
- C. Easy Cost Planning
- D. Project planning board
Answer: A,D
NEW QUESTION # 73
What are the prerequisites for delivering materials from the project? Note: There are 2 correct answers to this question
- A. A delivery document type must be configured
- B. A shipping point is necessary
- C. A sales order must be created in advance
- D. A sold to party is necessary
Answer: A,B
NEW QUESTION # 74
How can you update the degree of processing for an activity?
- A. By scheduling the activity
- B. By using results analysis
- C. By confirming the activity
- D. By changing the activity
Answer: C
NEW QUESTION # 75
Which statement is valid regarding networks?
- A. Relationships can be used to connect activities of different networks
- B. Material components can be assigned to activity elements
- C. A network activity can be assigned to several WBS elements
- D. A network can be activity-account-assigned and header-account-assigned
Answer: C
NEW QUESTION # 76
An external component is assigned to a network activity. The delivery date for the purchase requisition depends on the dates of the network activity. What controls whether the delivery date is defined by the earliest or latest scheduled dates?
- A. The control key
- B. The scheduling parameters for the network
- C. The table of MRP controllers
- D. The network profile
Answer: B
NEW QUESTION # 77
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A sales order must be created in advance.
- B. A sold to party is necessary.
- C. A delivery document type must be configured.
- D. A shipping point is necessary.
Answer: B,D
NEW QUESTION # 78
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct answers to this question
- A. Sales order
- B. Inquiry
- C. Billing
- D. Quotation
Answer: B,C
NEW QUESTION # 79
How can you grant individual authorization for WBS elements and networks?
- A. Activate access control lists (ACL) for the project profile and the network profile
- B. Set the system status to "Lock Master Data".
- C. Activate access control lists (ACL) for the user master record.
- D. Define a user status to lock the business transaction Update Project.
Answer: A
Explanation:
To grant individual authorization for WBS elements and networks, you have to activate access control lists (ACL) for the project profile and the network profile. Access control lists are a feature that allows you to control access to project objects, such as WBS elements and networks, based on user-specific authorization objects. You can use access control lists to define which users can create, change, display, or delete project objects. The project profile is a parameter that defines the basic properties of a project, such as its project type, number range, and budget profile. The network profile is a parameter that defines the basic properties of a network, such as its order type, number range, and scheduling parameters. You have to activate access control lists for both the project profile and the network profile in Customizing in order to use them for WBS elements and networks. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 80
Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question
- A. Baseline dates
- B. Basic dates
- C. Planned dates
- D. Forecast dates
Answer: B,C
Explanation:
Basic dates and planned dates are some of the sets of dates that can be used to schedule networks. Basic dates are the earliest possible start and finish dates of an activity or a network, based on its dependencies and constraints. Planned dates are the scheduled start and finish dates of an activity or a network, based on its basic dates and available capacities. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 81
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
- A. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
- B. You can only maintain the actual start of a WBS element if the finish date is not maintained
- C. You can always maintain the actual start and finish date of a WBS element
- D. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
Answer: A,C
Explanation:
If you are using WBS elements and activities are not assigned, you can always maintain the actual start and finish date of a WBS element manually or automatically. However, you can only maintain the actual start if the WBS element has the status "Released" or "Partially released", which means it is ready for processing or partially ready for processing. You can maintain the actual finish regardless of the status of the WBS element. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 82
What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question
- A. Resource
- B. Location
- C. Production version
- D. Material
Answer: A,D
Explanation:
PPIDS master data is necessary for using PP/DS, which is a component of SAP APO that provides advanced planning and scheduling functions for production planning and detailed scheduling. PPIDS master data includes material and resource data. Material is a set of data that defines the characteristics and properties of a product that can be produced or procured. Resource is a set of data that defines the characteristics and capacities of a production facility that can be used to produce products. Reference: https://help.sap.com/doc/saphelp_scm700_ehp02/7.0.2/en-US/69/f3055130534338e10000000a154ce5/content.htm
NEW QUESTION # 83
You are working with networks and WBS elements. Which of the following statements applies
- A. You can reassign an activity from one network to another
- B. You have to activate the operative indicator Account Assignment Element for WBS element with activities.
- C. You can assign the network header to multiple WBS elements
- D. You have to maintain a network profile in the project profile
Answer: D
Explanation:
One of the statements that applies to working with networks and WBS elements is that you have to maintain a network profile in the project profile. A network profile is a parameter that defines the basic properties of a network, such as its order type, number range, and scheduling parameters. A project profile is a parameter that defines the basic properties of a project, such as its project type, number range, and budget profile. You have to assign a network profile to a project profile in order to create networks within a project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 84
The__________________that you specify when you create a project definition is unique for the entire project. Choose the correct answer.
- A. Plant
- B. Controlling area
- C. Company code
- D. Planning department
Answer: B
NEW QUESTION # 85
Where do you maintain the length of the project ID?
- A. Project profile
- B. Project coding mask
- C. Project type
- D. Special characters
Answer: B
NEW QUESTION # 86
You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?
- A. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
- B. . Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt -> invoice receipt
- C. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
- D. Vendor selection -> Purchase order handling -> Invoice receipt- Purchase order monitoring -> Goods receipt
Answer: C
Explanation:
The sequence for the following business transactions and documents for external activities in a project is vendor selection -> purchase order creation -> service entry sheet creation -> service entry sheet approval. Vendor selection is a process that involves choosing a suitable vendor for providing external services for a project activity. Purchase order creation is an action that involves creating a document that contains the details of the service request and sending it to the vendor. Service entry sheet creation is an action that involves creating a document that records the delivery of services from the vendor and posting actual costs to the project. Service entry sheet approval is an action that involves checking and confirming the accuracy of the service entry sheet before paying the vendor. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 87
......
SAP C_TS412_2021 certification exam consists of 80 multiple-choice questions, and the candidate has three hours to complete the exam. C-TS412-2021 exam is available in English, Japanese, and Korean languages. The passing score for C-TS412-2021 exam is 63%, and the candidate receives a digital badge and a certificate upon passing the exam. SAP Certified Application Associate - SAP S/4HANA Project Systems certification is valid for two years, and the candidate needs to renew the certification by passing the relevant exam or completing the required continuing education.